Transmission Line Design

In addition to state and federal policies that would apply to any transmission line, there are numerous variables and choices that come into play when sitting down to design a new transmission line. Each of those choices from size, to location, to technology sets forth a specified list of requirements geared toward safety, reliable transmission of electricity and environmental protection.

Bulk Transmission = High Voltage Lines

The majority of major transmission lines in the U.S. are either 230-kilovolt (kV) or 500-kV alternating current lines. In some cases, 115-kV lines are used. Lower voltages are far less efficient for moving electricity across hundreds or thousands of miles to where it is needed without losing a significant amount of energy.

For safety reasons, the higher the voltage, the more distance is needed between the conductors and other objects such as trees, buildings or the ground. Though it is largely dependent on the surrounding terrain and the voltage level of the transmission line, in general, overhead high-voltage transmission lines are typically at least 30 feet off the ground.

Tower Varieties

For high voltage lines, there are generally two tower options for overhead transmission line towers - lattice steel and tubular steel towers.

Lattice steel towers are more prevalent and common, and they come in several familiar shapes and sizes. These can be supported by four concrete footings, or a combination of concrete footings and guide wires. The number of conductors going between each tower depends on whether the transmission line is single circuit (three wires) or dual circuit (six wires).

Tubular steel towers are relatively new; they consist of a single steel pole anchored into the ground. These can be more visually appealing than their lattice steel counterparts, although historically they have been more costly to construct and can result in increased maintenance costs and requirements.

Clearance Requirements

Clearance requirements relates to a few issues, primarily the height of the wires from the ground and other permanent structures, the distance that must be between two towers in a single transmission line (or the distance between towers from two or more separate transmission lines built within a single transmission corridor), and the proximity of transmission lines to roads and highways. These requirements are mandated by federal, state and (sometimes) local governments and the specific requirements are a function of exactly where the line and towers will be located.

Reliability Standards

Reliability standards are closely related to clearance requirements. In short, this means ensuring the lights will stay on in the event of a tower collapse of other major failure along the line.

Co-Location

Co-location involves the addition of a new transmission line to pre-existing transmission infrastructure. Clearance requirements and reliability standards both come into play when co-location is being considered. One key question to consider is whether an existing tower can support the added weight of an additional set of wires. If the answer is no, a tower upgrade might be a solution.

The risk of co-location, however, is that this option leaves two transmission systems to rely on a single set of towers. If one of those towers fails, both lines go down.

Another question that is asked frequently when routes for transmission lines are being considered is whether the new line could be built alongside a pre-existing line. In these cases it is incumbent upon the planners to ensure both lines would not be lost in a single event (e.g., a tower from Line A collapses, crashing through Line B and taking both transmission systems out). If this can't be established, the minimum distance between the two lines must equal at least a span length between the towers. On a typical 500-kV line, this would be 1,250 feet; just shy of a quarter mile. That could easily position a route outside of a narrow existing corridor or into a development, park, highway or other pre-existing development.

A third question surrounding co-location involves whether the line can be located alongside other major infrastructure right of ways such as a freeway or railroad tracks. Federal, state and local regulations involving right-of-ways will hold sway over that decision, as will a focus on avoiding public safety risks from traffic accidents involving the line.

Upgrading

One possibility planners may look at is whether an existing transmission line could be upgraded to a higher voltage, enabling the delivery of an increased amount of electricity without building an entirely new line. A key question (outside the issue that doing so won't enhance reliability of the system via a new and redundant transmission line) is whether the current structure of a given line can support an upgrade. For example, going from 230-kV to 500kV requires the use of bigger, heavier wires, which might necessitate the construction of additional towers along the route to support the added weight.

Undergrounding

It is possible to bury transmission lines underground instead of building an overhead system connected by a series of steel towers, but, here too, there are tradeoffs and requirements for public safety and the environment. Beyond the increased cost of undergrounding transmission lines (10 to 30 times greater than overhead construction depending on voltage), the main issues are heat and environmental impacts.

When high-voltage energy flows through a conductor, resistance in the conductor generates waste heat (or transmission losses). The higher the energy transmitted, the more heat is generated. With overhead transmission lines, the air surrounding the lines acts as an insulator and absorbs this waste heat. In underground transmission lines other mediums must be used to dissipate this heat, which to-date has restricted the undergrounding of transmission lines to voltages less than 500-kV except for very short distances.

Another consideration of underground lines is the ground disturbance caused by the tunnels through which the transmission line runs. Instead of impacting the ground only at tower footings, underground transmission construction requires extensive excavation and can disrupt habitats or water resources. Additionally access to the underground transmission line, which is needed for maintenance and repairs, requires construction of "vaults." These vaults are typically 20' x 30' structures (roughly the size of an average living room) that must be buried in the ground every 750-1,000 feet where the conductors are spliced together. The environmental and land disruption impacts of undergrounding transmission lines can greatly exceed that of above ground transmission, and are factors that are weighed in the planning process.


Glossary
The Big Picture
Transmission Q&A
Research and Reports

 

 

Stay Informed! Learn more about how we are keeping the lights on in California! Signup for TANC updates to keep up on the latest energy news.

Copyright 2012 Transmission Agency of Northern California. All rights reserved.